Bartz Way Paving Project Road Closure
June 9, 2025

Beginning June 11, a portion of the road connecting Terry Street and Bartz Way will be closed for approximately four weeks as part of the multi-phase Bartz Way paving project. Traffic will be detoured through the Reed Gym parking lot.
This phase, phase 5, is expected to take approximately four weeks, with completion anticipated around July 11. This timeline is weather-dependent and may change due to unforeseen site conditions, such as soft spots under the roadway.
Detour signage will be in place to guide traffic. Please follow all posted traffic control signs, detour instructions, and barriers for everyone’s safety.