11:00 pm Wednesday, July 1 Through 6:00 am Thursday, July 2

IT Services:

The following servers/services are scheduled for maintenance during the weekly Wednesday Information Technology Services (ITS) maintenance window: 

 

Network Connectivity in all Pocatello buildings EXCEPT:

·         BA-B13 and BA-B50 – Data Centers

·         Building 46, 48, 49 and 51 in the COT complex

·         Building 89: Linea Accelerator Center

 

Wireless Network

 

VoIP

Impact:

 

A test of UPS’s for all building network switches will occur during the maintenance window.  Should a UPS fail during the test, a network outage will occur for that building.   

 

Additionally, all wireless control modules will be upgraded during this maintenance window.  Please plan for wireless network outages.

 

The VoIP services will be upgraded to the newest release of software.  There should be no interruption in services as all call processing is redundant (one server at a time will be upgraded).  The Boise VoIP server will add to this  cluster in preparation of the Meridian move.